Hollandse Kust Zuid Offshore Wind Farm Grid Connection in the Netherlands.
Contact
AB
Andrea Brambilla
Associate Director
Share

Project overview

Complex delivery

TenneT’s Alpha and Beta 700MW transformer platforms are components of the critical infrastructure needed to connect energy generated from the HKZ offshore wind farm to land.

Maintaining programme milestones to support wind farm development and installation is a huge challenge. This is due to the complex requirements and risks involved when building and installing large infrastructure and electrical equipment at sea. Major threats to progress include low productivity during fabrication, and quality issues that could potentially delay connection of the wind farm to the grid.

Concern that the COVID-19 pandemic was impacting fabrication of the transformer platform topsides, and critically, their forecast completion date, TenneT commissioned us to provide a project performance assurance service including progress monitoring, progress measurement and verification.

The services included project management and project controls advice during the fabrication phase.

Critical for TenneT was assurance that the fabrication schedule, including onshore testing and commissioning, was on track to meet the project’s Ready For Sail Away (RFSA) date and all subsequent transportation and installation commitments.

Project story

Meeting critical construction milestones

Collaborating with TenneT’s Engineer, Procure, Construct and Install (EPCI) contractor, we rapidly mobilised and led an independent Joint Task Force comprising planning, project controls and quantity surveying specialists at the fabrication site in Dubai.

At the Dubai Drydocks, we delivered our industry best practice solutions for construction progress measurement.

Deploying our quantity, weight and cost assurance service, QuanTTum, we were able to analyse and measure the quantities required for the topside and jacket from Alpha and Beta’s 3D models, enabling the development of an accurate bill of quantities and creation of a schedule and progress measurement system (PMS) built on measured quantities.

The PMS provided a clear and transparent audit trail of installed quantities and accurate, actual weekly progress, providing assurance, or adjustment where necessary, of the forecast completion, sail-away, transportation and installation dates.

Power BI was used to present dashboard status updates on progress, providing clarity and a single source of truth for senior management.

We also used the Matterport visual image capture and measurement tool to maintain an accurate status of offshore fabrication completion and allow progress of the offshore hook up and commissioning (HUC) phase to be monitored remotely.

Crossing borders, connecting countries

TenneT’s key objective is to deliver a secure and continuous supply of electricity. The high-voltage grid is the backbone of the electricity supply system, connecting electricity producers to consumers, connecting and integrating electricity markets.

We continue to work closely with TenneT to identify opportunities to improve project set up and delivery of future grid connection developments.

 

“TenneT is committed to facilitating the Netherlands' ambitions for offshore wind. It has been a challenging year and Turner & Townsend has supported us in maintaining control and meeting the programme milestones of the critical infrastructure required to connect HKZ.”

Joris Engelen
Project Lead Platform
TenneT 

728799445 thumbnail
The project in action
Go behind the scenes with the team on this ambitious project
related

You might also be interested in these projects

Windmills of the first row, and a few of a second row are visible in a large wind farm
Kenya

Powering Kenya's clean energy future with Lake Turkana Wind Power

3 min read

The DolWin epsilon converter station (an solid, yellow structure) floating in the sea.
Singapore, Norway, Germany

Meeting green energy needs with TenneT and the DoIWin Epsilon Converter

3 min read

Wind turbines on a green field
Germany

Meeting Germany's future green energy needs with TenneT

2 min read

Ocean floor shot of the Celtic Interconnector, Ireland.
Ireland

Delivering the Celtic Interconnector with EirGrid

1 min read

EXPLORE MORE
A group of employees having a casual chat in the break room with a table with apples.
Services
Battersea Power Station lit up at night, view from the Thames with buildings in the backgroundImage courtesy: Placeholder
Sectors
Male and female colleagues having a casual chat in the break room.
Join us